P18419: Hydroponic Monitoring System
/public/

Integrated System Build & Test

Table of Contents

Team Vision for Integrated System Build & Test Phase

Test Results Summary

Flow Sensor Performance

Flow Sensor Results

Flow Sensor Results

EC Sensor

EC Sensor Results

EC Sensor Results

Electrical Box

Components Placement

Components Placement

Sensor Holder Prototype

Sensor Holder

Sensor Holder

Test Plan Document

Software

Software Layout

Software Layout

Mechanical System

public/Photo Gallery/isbt_mLayout.png
public/Photo Gallery/isbt_mLayout2.png

Risk and Problem Tracking

Risk and ProblemTracking

Risk and ProblemTracking

Risk and ProblemTracking

Risk and ProblemTracking

Functional Demo Materials

Plans for next phase

Team Member Three week plan
Nate
  • Put all components in electrical box with most efficient layout (1 class) - Deadline: 3/29/18
  • 3D print different fixtures to hold the sensors (4 Hours) - Deadline: 3/29/18
  • Run all components in box with a thermometer to get max temperature (1 class) - Deadline: 4/3/18
  • Get data from full system for PH and 02 (1 Class) - Deadline: 4/17/18
Ryan
  • Confirm location for Imagine RIT - (2 weeks) Deadline: 4/12
  • Build main unit - (1 week) Deadline: 4/3
  • Build additional units - (3-4 weeks) Deadline: 4/28
  • Write a how-to manual - (3 weeks) Deadline: 4/19
  • Work on final paper and poster - (2 weeks) Deadline: 4/12 and 4/05
Kevin
  • Finish construction on a Mechanical Operational System before plants arrive, shipped April 17th, Deadline:4/17/18
  • Write technical paper on mechanical design Hard Deadline 4/12/18
  • Work on poster for Imagine RIT Deadline: 4/5/18
Ray
  • Optimize fitment of components within electrical box (2 hours)
  • Conclude design / placement of air pump (2 hours)
  • Assist in sensor testing / building mechanical structure (2 weeks)
  • Work on final paper (2 weeks) - Hard Deadline 4/12/18
Thierno
  • Test and Optimize EC sensor
  • Work on layout poster and consider important things to show Deadline: 4/5/18
  • Assist in sensor testing / building mechanical structure (2 weeks)
Jerry
  • Finish testing multiple client communication
  • Continue testing sensors
  • Work on final paper Deadline 4/17/2018
  • Work on poster for Imagine RIT 4/05/2018

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation