P18422: Black Soldier Fly Composting Habitat Improvement
/public/

Planning & Execution

Table of Contents

Intellectual Property Considerations

The Lords of the Flies do not foresee any situations in which Intellectual Property will be a concern. Throughout the entirety of this project, the majority of the work will be based on universally known systems and processes. In the event that the need does arise for the group to develop Intellectual Property, it will be further discussed at that time.

Team Setup

Member Role Skills Email
Saeed Akbar Electrical Coordinator AutoCAD, Verilog, Electrical Wiring, VHDL sxa9062@rit.edu
Daniel Berg 3D Modeling Lead (MSD 1) Autodesk Inventor, Matlab, Machining dgb4471@rit.edu
Craig Brzyski Webmaster, Programmer C Coding Language, Assembly Language, HTML/CSS, Electrical Wiring cab1861@rit.edu
Lauren Cussen Facilitator/Communicator, Purchasing Specialist (MSD 2) MATLAB, Solidworks, LabView lnc5608@rit.edu
Ian Lengel Purchasing Specialist (MSD 1), 3D Modeling Lead (MSD 2) Solidworks, Composites, AutoCAD ipl9550@rit.edu
Melissa Nellist Lead Engineer Machining, Time Management, Research and Information Gathering mjn5439@rit.edu
Corey Wrigley Project Manager Design of Experiments, Data Analysis (.R and Minitab), Project Management caw7107@rit.edu

Team Values and Norms

Please refer to the Values and Norms page or view the Values and Norms Document to understand the values and expectations that guide the team.

Project Plans & Schedules

MSD 1 Project Plans

Link to our Preliminary Project Plan.

Link to our Systems Design Project Plan.

Link to our Preliminary Detailed Design Project Plan.

Link to our Detailed Design Project Plan.

MSD 1 Visions and Schedules

Link to our Systems Design Vision and Schedule.

Link to our Preliminary Detailed Design Vision and Schedule.

Link to our Detailed Design Vision and Schedule.

MSD 2 Project Plans

Link to our Project Plan for the start of MSD 2.

Link to our Subsystem Build & Test Project Plan.

Link to our Integrated System Build & Test Project Plan

Link to our Customer Handoff & Final Project Documentation Plan

MSD 2 Visions and Schedules

Link to our Team and Individual Visions Document for the Prep Phase.

Link to our Build & Test Prep Vision and Schedule.

Link to our Subsystem Build & Test Vision and Schedule.

Link to our Integrated System Build & Test Vision and Schedule

Risk Assessment and Growth Curves

Link to our Risk Management Matrix Document as seen in the photo below.

The below table is the most up-to-date Risk Assessment Matrix for the project:

Risk Management Matrix

Risk Management Matrix

The following provides a summary into the mitigated risks associated with the project:
Mitigated Risks

Mitigated Risks

Changes of risks' impacts can be found below:

Plotting Impact over Time between Problem Definition and Systems Design Phases

Plotting Impact over Time between Problem Definition and Systems Design Phases

Plotting Impact over Time between Systems Design and Preliminary Detailed Design Phases

Plotting Impact over Time between Systems Design and Preliminary Detailed Design Phases

Plotting Impact over Time between Preliminary Design and Detailed Design Phases

Plotting Impact over Time between Preliminary Design and Detailed Design Phases

Plotting Impact over Time between Detailed Design and Build & Test Prep Phases

Plotting Impact over Time between Detailed Design and Build & Test Prep Phases

Plotting Impact over Time between Subsystem Build & Test and Integrated System Build & Test Phases

Plotting Impact over Time between Subsystem Build & Test and Integrated System Build & Test Phases

Plotting Impact over Time between Integrated System Build & Test and Customer Handoff & Final Project Documentation Phases

Plotting Impact over Time between Integrated System Build & Test and Customer Handoff & Final Project Documentation Phases

Impact Table over Time

Impact Table over Time

Other Team Resources

Meeting Minutes, Notes, & Actions

Available through the Meeting Minutes and Communications Page.

Peer Reviews

During the Design Review Meeting, the group was being evaluated by other groups. Each of our peers completed and returned the Peer Review Document to our group.

Communication

Project Reviews

Please reference the project information available in the Problem Definition page.

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation