Team Vision for Build & Test Prep Phase

Summarize: During this phase the team will perform several tests and complete a list of tasks that will lead up to the building of the filament extruder.

Test Plan Summary

Use your test plan to summarize test results and assess effectiveness of test plans to unambiguously demonstrate satisfaction of the engineering requirements

Instructions

  1. Ensure test plans are in place
  2. Ensure that all applicable test standards have been cited (e.g., ASTM)
  3. Ensure all ordered materials have been received
  4. Ensure team has space and equipment necessary to begin building and testing

Risk and Problem Tracking

Design Review Materials

Design Review Week 2 Include links to:

Design Review Week 6

Plans for next phase


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation