P18718: ISE Utility Infielders
/public/

Detailed Design

Table of Contents

Team Vision for Detailed Design Phase

During this phase, our team completed the following:


Updated Customer and Engineering Requirements

Updated Customer Requirements

Updated Customer Requirements

Updated Customer Requirements

Updated Engineering Requirements

Updated Engineering Requirements

Updated Engineering Requirements

Test Plans

The following test plans are broken up into 3 categories and the estimated projected settings are provided next to each description.

Visual Management Improvements

Visual Management Improvements

Adjustment Reduction Improvements

Adjustment Reduction Improvements

Process Improvements

Process Improvements

Risk Assessment

The following risks were added in the Detailed Design Phase.

Risk Assessment Update

Risk Assessment Update

Access to the live Risk Management document can be accessed here.

Design Review Materials

The full Detailed Design presentation can be accessed here.

Plans for next phase

For this semester, we have met the targets for 4 out of 5 main goals.

Gantt Chart

Gantt Chart

Our 6 week plan starting in MSDII will consist of the following.

6 Week Plan

6 Week Plan


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation