Team Vision for Preliminary Detailed Design Phase

Summary of Work Completed

During this phase, the team was able to complete the following:

Prototyping, Engineering Analysis, Simulation

Iterative activities to demonstrate feasibility, including assumptions you made in your analyses or simulations. Have you completed sufficient analysis to ensure that your design will satisfy requirements? Have you included all usage scenarios in your modeling?

Feasibility: Prototyping, Analysis, Simulation

Proposed Changeover Utilizing Workers and Parallel

The following structure to the 3P Changeover utilizes two workers in parallel. When the steps in the time study were rearranged for two workers in parallel, the total time decreased from 416 seconds to a projected total time of 311 seconds. The projected time is 25% less than the time study for the first changeover. The bolded steps are where the operators work together, and an operator with more experience may act as "Operator 1" in the proposed changeover.

Parallel Breakdown of Work Steps

Parallel Breakdown of Work Steps

Drawings, Schematics, Flow Charts, Simulations

8 Wastes

From analyzing the first changeover video and the process in person, we were able to determine the following wastes within the changeover process. The wastes stated are primarily focused on the 3P Packaging area.

8 Wastes: TIMWOODS

8 Wastes: TIMWOODS

Test Plans

Purpose

Demonstrate objectively the degree to which the Engineering Requirements are satisfied. The following test plans are not yet prioritized, but will be prior to the next design review phase.
Test Plans

Test Plans

Desired Outcomes from Test Plans

Desired Outcomes from Test Plans

Design and Flowcharts

Fishbone Diagram

Going into the 3rd Phase, the Fishbone diagram was updated to include the Methods category.

Fishbone Diagram for Changeover Times

Fishbone Diagram for Changeover Times

Risk Assessment

Many of the risks are low severity items external of our project. The top four risks can be seen in the snapshot below.
Top Four Risks

Top Four Risks

The complete list of risks can be seen in the following Risk Management document.

Design Review Materials

The full Preliminary Detailed Design presentation can be accessed here.

The notes after the meeting can be accessed here.

Plans for next phase

During the next three weeks, we would like to complete the following.

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation