Team Vision for Build & Test Prep Phase

During this phase the team:

Test Plan Summary

The team first went through the Engineering Requirements and updated them based on the progress and outcomes during MSD I. The team then created test plans for each requirement. They are outlined in the table below.

Test Plans

Test Plans

Risk Tracking

The current Risk Table is below.

Risk Table

Risk Table

Plans for next phase

The plan for the first six weeks of MSD II is below. At this point, the team is up to date on all Phase 5 items and on track to move forward to Phase 6.

MSD II Phases 5 and 6 Plan

MSD II Phases 5 and 6 Plan

Leigh's individual six week plan can be found here.

Chris's individual six week plan can be found here.

Jess's individual six week plan can be found here.

Brandon's individual six week plan can be found here.


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation