Customer Handoff & Final Project Documentation

Table of Contents

Team Vision for Final Demo and Handoff

Current Phase Plan Progress

Order PCB

Continue Tests

Integrate Battery Checking into Dext

Complete Game

Finish wearable mechanical prototype for testing

Write the Technical Paper

DEXT

DEXT

Test Results Summary

Test Plans

Test Plans

Test Completed? Current Status? Within Current Scope?
S1 - Communication Delay Complete Completed Within Current Iter Scope
S2 - Battery Life Not Started Waiting for start Within Current Iter Scope
S3 - Recharge Rate Not Started Waiting for start Within Current Iter Scope
S4 - Weight Started Waiting for final prototype to weigh Within Current Iter Scope
S5 - Vertical Profile Completed Conclusion needs to be Written Within Current Iter Scope
S6 - Adjustability Completed Conclusion needs to be Written Within Current Iter Scope
S7 - Comfort Completed Complete Within Current Iter Scope
S8 - # of Possible Controls Not Started Waiting for start Within Current Iter Scope
S9 - Durability Completed Conclusion needs to be Written Within Current Iter Scope
S10 - Removal / Equip time Completed Conclusion needs to be Written Within Current Iter Scope
S11 - Cycle Testing Not Started Waiting for start Possibly outside of Current Scope
S12 - Cable Strain Durability Not Started Waiting for start Possibly outside of Current Scope
S13 - Functionality/Enjoyable Not Started Testing During ImagineRIT Within Current Iter Scope

The current Test Plans can be found here.

Updated BOM

This is the currently up to date BOM of orders that have been made since last review. As can be seen, with total spent at $575.64, we are well within our $1500 budget, so we should be able to create more than one prototype for ImagineRIT as well as possibly have a meal on the Team for the Guide and Sponsor.
Updated BOM

Updated BOM

The BOM file can be found here.

Risk and Problem Tracking

The Risk Management chart has been updated to reflect the team's progress on the prototype's development. The current and updated Risk Management chart can be found here.

The issue where the mechanical case was not being developed due to Willow being overwhelmed was resolved by having Sarah take over the development of the casing. While this should have been done sooner to save time, it looks like we should be able to get a functional prototype done despite the setbacks.

Problem Tracking

Problem Tracking

We once again had an issue with PCB ordering, although this time it was due to someone in the office not selecting swift service for our board, thankfully it should arrive in time for ImagineRIT. The Problem Tracking Document can be found can be found here.

Final Project Documentation

DEXT Final project Documentation & Demo Materials
Final Dext Poster
Dext Technical Paper
Review Presentation

Plans for Wrap-up

ImagineRIT Approaches and the Team is planning to get the sleekest, comfortable, functional, wearable prototype we can manage in this short time to be at our table at Imagine this year. We intend to finish up our Test Plans and subsequently our Technical Paper.

The team's individual plans for the next phase are available in the table below

Team Member Wrap-Up Plans
Willow
Jon
Nick
Sarah
Tim
Alice
Vincent

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation