P19014: Portable Upright Walker
/public/

Gate Reviews

Table of Contents

Your team will hold a gate review with your guide at the end of each semester. This page should document any information needed for the review, as well as outcomes.

MSD I: Readiness to move to Build & Test

Expectations

Status Review

Current state of the project
Comparison of risk assessment

We have assessed the risk surrounding this project. At this time, no risks appear unaccounted for. The addition of human subject research testing may bring about additional risks, however the safety of the device has been assured through testing. The risk of falling still applies to the trials as well as everyday use.

At first, we did not account for the risks associated with external resources. Since the aspects of manufacturing and tube bending require assistance from sources within various labs on campus, we must adapt to this constraint and plan ahead in order to minimize the risk of conflict when planning to work with these important resources.

Review your team's MSD II schedule (if not done during DDR)

Deliverables Checklist and Website Status

MSD II: Project close-out

Expectations

Status Review

Current state of the project

Deliverables Checklist and Website Status

Lessons learned, etc.


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation