Team Vision for Subsystem Level Build & Test Phase

Goals Accomplishments Future Tasks
  • All parts machined
  • All parts ordered
  • All Sub-Assemblies constructed
  • Be prepared for Sub-system functional demonstration at end of phase
  • 90% parts machined
  • all determined parts ordered besides steel coupler, switches placement, and battery
  • Throwing sub-assembly assembled
  • Testing partners confirmed
  • Complete Catching sub-assembly
  • Complete systems integration
  • Complete testing
  • Complete paper, poster, an exhibit plans

Updated BOM

Updated Phase VI BOM

Updated Phase VI BOM

The updated Bill of Materials can be found here

Assembly Instructions

Catching Subsystem Assembly Instructions

Catching Subsystem Assembly Instructions

Launch Subsystem Assembly Instructions

Launch Subsystem Assembly Instructions

Launch Subsystem Assembly Instructions

Launch Subsystem Assembly Instructions

Assembly

public/Photo Gallery/PIc1.jpg

public/Photo Gallery/pic2.jpg

public/Photo Gallery/pic3.jpg

Assembly Notebooks

 Launch Assembly Notebook

Launch Assembly Notebook

Finalized Test Plan

 Test Plan Summary

Test Plan Summary

Additional Notes

Risk and Problem Tracking

Updated risks in Phase VI

Updated risks in Phase VI

 Risk Curve

Risk Curve

Problem Tracking in Phase VI

Problem Tracking in Phase VI

Functional Demo Materials

Plans for next phase

 Phase VI Individual Task List

Phase VI Individual Task List

 Phase VII Schedule

Phase VII Schedule

 MSD PERT

MSD PERT


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation