P19104: HABIP-BioX
/public/

Preliminary Detailed Design

Table of Contents

Team Vision for Preliminary Detailed Design Phase

Detailed block diagrams of each sub system were created. Analysis and prototyping were performed where necessary to gain insight on the best solution. The team worked on completing schematics for all of the boards in the system.

System Architecture Preliminary Detailed Design

System

System

The System Architecture Preliminary Detailed Design page goes through the preliminary detailed design of the system.

DACQ/CBOB Preliminary Detailed Design Phase

The block diagram for the Data Acquisition Board (DACQ) is shown below.

DACQ

DACQ

The block diagram for the Cluster Breakout Board (CBOB) is shown below.

DACQ

DACQ

The DACQ and CBOB Preliminary Detailed Design page goes through the preliminary detailed design of the DACQ and CBOB.

BioCell Preliminary Detailed Design Phase

The functional decomposition of the BioCell is shown below.

BioCell

BioCell

The BioCell Preliminary Detailed Design page goes through the preliminary detailed design of the Biocell.

Communication System Preliminary Detailed Design Phase

The functional decomposition of the communication is shown below.

Comm Functional Decomposition

Comm Functional Decomposition

The data transfer of the communication is shown below.

Communication Board Data Block Diagram

Communication Board Data Block Diagram

The Communication System Preliminary Detailed Design page goes through the preliminary detailed design of the communication system.

Power Selection Process

The functional decomposition of the Power System is shown below.

Solar

Solar

A block diagram of the power system is shown below.

Power System Block Diagram Block Diagram

Power System Block Diagram Block Diagram

The Power Preliminary Detailed Design page goes through the preliminary detailed design of the system.

Structure Selection Process

The functional decomposition of the structure is shown below.

Structure

Structure

The Structure Preliminary Detailed Design page goes through the Preliminary Detailed Design of the structure.

Bill of Material (BOM)

The budget we breakdown of the team that we are sticking to going forward is shown below:

SF1 System BOM

SF1 System BOM

The category "Other" is set aside for any unforseen costs going forward, and has been allocated to be ~20% of our total budget.

A portion of the high level BOM that contains most of the parts from the various subsystems is shown below.

SF1 System BOM

SF1 System BOM

A link to the working document can be found here: Preliminary Detailed Design Documents/Master_BOM.xlsx

SF1 Budget

SF1 Budget

SF1 Part Cost Breakdown

SF1 Part Cost Breakdown

Test Plans

As we started to write test plans, we realized that there were a few engineering requirements (ERs) that should be updated and/or added to have a more robust list that would satisfy all the customer requirements (CRs). The updated list with the updated material being highlighted can be found here:

Preliminary Detailed Design Documents/Updated_ERs_Prelim_design.xlsx

A document listing the test plans that will address all of the engineering requirements of the entire system can be found here.

Preliminary Detailed Design Documents/Test_Plan_w_ERs.xlsx

Design and Flowcharts

A block diagram of the entire system is shown below.

Power Distribution

Board Diagram

Board Diagram

Data Connections

Board Diagram

Board Diagram

Risk Assessment

The risks identified to be the most relevant to the preliminary detailed design phase are shown below:

Preliminary Detailed Design Risk Assessment 1

Preliminary Detailed Design Risk Assessment 1

Preliminary Detailed Design Risk Assessment 2

Preliminary Detailed Design Risk Assessment 2

A link to the full document containing the risks identified in all project phases can be found here:

Preliminary Detailed Design Documents/Preliminary_Detailed_Design_Risk_Assessment_Revisited.xlsx

Design Review Materials

A link to the Pre-Read is here: Preliminary Detailed Design Documents/Preliminary Detailed Design Review.pptx

A link to the notes taken from the presentation is here: Preliminary Detailed Design Documents/Preliminary_Detailed_Design_Presentation_notes.docx

Plans for next phase

As a team, we want to have all PCBs sent out to be made by the end of the semester. Also, we want to have a detailed CAD model done of the entire structure as well as the biocell.

Schedule

A Gantt chart describing the schedule for the next phase of MSDI is included here: Preliminary Detailed Design Documents/SF1_Schedule.pdf

Three-week plans for individual team members:

Member Three-Week Plan
Braeden Morrison 3_week_plans/Detailed_Design/BJM_3_Week_Plan_for_Detailed_Design.docx
Larissa Plaskon 3_week_plans/Detailed_Design/LFP_3_Week_Plan_for_Detailed_Design.docx
Jacob Felice 3_week_plans/Detailed_Design/JTF_3_Week_Plan_for_Detailed_Design.docx
Andrew Eberhard 3_week_plans/Detailed_Design/AJE_3_Week_Plan_for_Detailed_Design.docx
Joe Payne 3_week_plans/Detailed_Design/JDP_3_Week_Plan_for_Detailed_Design.docx
Ryan Tatu 3_week_plans/Detailed_Design/RNT_3_Week_Plan_for_Detailed_Design.docx
Ben Cooper 3_week_plans/Detailed_Design/BEC_3_Week_Plan_for_Detailed_Design.docx

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation