Team Goals For This Review

Goal Status
Finalize a complete design output Completed
Update and complete all design documentations Completed
First Draft of MSD II plan Completed
Complete ER Completed
Complete Risk Assessment Completed
Order any long lead-time parts Completed

Problem Definition Recap

As a continuation of project P18310. Project P18310’s purpose was to build two vibrating mass systems to demonstrate the effectiveness of LORD’s TVA (Tuned Vibration Absorber) technology at trade shows and academic presentations. Project P19310’s goal is to take the existing unit and refine the design and software to create a more effective and portable solution.

The key goals of this project are:

The key constraints for this project are:

Progress Report

 Current Progress Report

Current Progress Report

Design Detail

System Architecture

 Trade Show Full Setup

Trade Show Full Setup

 Electric Box Design

Electric Box Design

System Architecture

System Architecture

BOM

 BOM Summary

BOM Summary

 Budget Breakdown

Budget Breakdown

Electrical System and MATLAB

 Wiring

Wiring

 Electric Box Design

Electric Box Design

 System Operation Flowchart

System Operation Flowchart

 System Setup Flowchart

System Setup Flowchart

 GUI Design

GUI Design

mechanical system

 Full System Setup

Full System Setup

 Full Assembly

Full Assembly

 Drawing Update

Drawing Update

Test Plans Addressing Engineering Requirements

 ER and Test Plans

ER and Test Plans

Project management

Risk Management

 Resolved Risks

Resolved Risks

MSD II plan

 MSDII Rough Plan

MSDII Rough Plan

Lessons Learned

Upon completion of MSDI , a few lessons were learned :

Suggestions for MSDI :


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation