Team Vision for Problem Definition Phase

Our team attempted to accurately define our problem with the help of our customer, as well as begin to develop a plan to move towards each deliverable.

Our team has a good understanding of the task at hand and we have organized our customer and engineering requirements based on the end goal of the product.

Project Summary

The main aim of this project is create a new platform to build and assemble a remote car that can autonomously navigate a track. The NXP car is used as a reference to develop a working car model so that students in the Interface Digital Electronics (IDE) can learn how to interface and program a small car to autonomously navigate . The primary input for the control algorithm is a camera that will be mounted on the chassis which can cover the entire width of the track at once. The track is two foot wide polymer with a one inch black stripe on each side of the track. The redesigned car should be easy to assemble, withstand minor crashes and cost effective at the same time. The target budget is $300 (or less) and should not exceed $400. The expected deliverables are working car model, detailed drawings, documentation of test results followed by a technical paper and a poster.

Use Cases

Use for the computer students in the IDE Course
Use Scenario 1

Use Scenario 1

Providing race car kit to High School STEM programs

Use Scenario 2

Use Scenario 2

Project Goals and Key Deliverables

We will deliver:

Customer Requirements (Needs)

Customer Requirements

Customer Requirements

Engineering Requirements (Metrics & Specifications)

Engineering Requirements

Engineering Requirements

Constraints

The Project Constraints are :

House of Quality

House Of Quality

House Of Quality

Project Risks

Project Risks

Project Risks

Plans for next phase

Phase 1 Plan

Phase 1 Plan

Phase 2 Plan

Phase 2 Plan

Links to Individual 3 Week Plans:

Jack's Three-Week Plan

Brian's Three-Week Plan

Fatma's Three-week Plan

Cam's Three-week Plan

Safwan's Three-week Plan

David's Three-week Plan


Home | Planning & Execution | Imagine RIT | Problem Definition Documents

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation