Team Vision for Build & Test Prep Phase

What did your team plan to do during this phase?

What did your team actually accomplish during this phase?

Test Plan Summary

To get our test plans organized we constructed a test plan summary that contains the various test we plan to perform during this phase. All test plans are based on our Engineering Requirements. Here is our test plan summary.

Risk and Problem Tracking

Below are our current risk.
Risks

Risks

Risks

Risks

From our risks we have discussed which risks could potential to become a problem for our project if not resolved. In order to prevent any future problems with our project we have come up with various solutions to overcome them. Here is a live document to our problem tracker.

Design Review Materials

Plans for next phase

Below is our teams plans for next phase.
Next Phase Plans

Next Phase Plans

Three Week Plans

Below are our individual three week plans.


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation