Integrated System Build & Test

Table of Contents

Team Vision for Integrated System Build & Test Phase

What did we planned to do during this phase?

What did we actually accomplished during this phase?

We ran into many unforeseen issues this phase that made us fall further behind in our proposed timeline. Because of this, we plan on work diligently to have as much a finished prototype as we can, with the proposed testing also completed.

Build Summary

Here is an update on our prototype. Because of the problems that we faced during the previous couple of phases, the prototype was unable to be completed in the time we factored in, so we will be working diligently to finish it in the final phase.

Below are some images on the process that we did to complete the foam mold that would be used to create the fiberglass molds that could then be reused with the cement pouring process:

Paper Cut-Outs

Paper Cut-Outs

Foam Cut Out

Foam Cut Out

Here are some finished, or partially finished, molds for the prototype:

Inside Foam Mold

Inside Foam Mold

Inside Foam Mold with Fiberglass Layer

Inside Foam Mold with Fiberglass Layer

Diverter Mold with Bondo

Diverter Mold with Bondo

Risk, Problem Tracking & Testing

Here are some live documents for our risks, problem tracking and testing sheets:

Plans for next phase

Here is our Gantt Chart for the upcoming and final phase:
Plans for Next Phase

Plans for Next Phase

Here are our final 3-week plans for Phase VIII:


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation