Team Vision for Detailed Design Phase
Plan for this phase is to keep building upon the preliminary design review and finalize all schematics, feasibility, flowcharts, Bill of material (order all parts before winter break) and schedule our priority dates and plans for MSD-II which the team was able to accomplish in this phase.
Progress Report
Team's progress in this phase was coming up with final- software design, status light, electrical schematics, test plans, and budget projections. Tasks that team needs to complete before MSD-II or start of MSD-II is to construct a POST at the observatory (Issue - Ground frozen) and contact previous team member for motor/software running assistance.Feasibility: Prototyping, Analysis, Simulation
Feasibility - Run Integrated System
Single Parent Software vs Individual Control Systems:- Single Parent Software:
- System is more streamlined
Multiple Related Software:
- Much more difficult to determine failure modes
- Multiple module components (Logically unconnected)
- Mess in general
Feasibility - Wake up/Go to sleep
Read data from an online weather service:- Query data from HTML to write sun rise and sunset times to a .csv file that can be read by the system’s controlling software.
Feasibility - GUI
Modify and improve the current LabView GUI:- Base is already built from previous team(s) - time savings
- Necessary to improve functionality of GUI.
Build web based application:
- Would require brand new application to be build - much more time
- Need to update ASRAS website anyways
Feasibility - Error Monitoring
MSP430:- Much more power efficient than Arduino
- Serial Communication
- Experience using the MSP430
- Previous teams already planned on using this hardware
LED Detection on Security Camera:
- Already checked regularly so the LED will be noticed quickly
Feasibility - Weather Protection
Read wind speed from the sensor - Most accurate, instant reading allowing dish to immediately go into a safety positionSnow - Not so straight forward. Read data from online weather service to prepare dish for upcoming storms
Feasibility - Interference Reduction
- Plan to continue with horizontal dipole setup
- Investigate whether this is the best solution or if there are other potential improvements to the current set up
- Involves extensive RF testing and validation
Feasibility - Storage
500 GB SSD
- 15 min FIT file ~ 760 kB
- 24 hours of data at 15 minute intervals ~ 96 data point per day
- 24 hours of data ~ 73 MB per day
Assume up to 200 MB per day with various other files
- 500 GB / 200 MB = 2500... 6.85 years of data
Drawings, Schematics, Flow Charts, Simulations
The schmeatics stayed the same as the previous team (18571).Bill of Material (BOM)
Engineering Requirements | Test Plans
Engineering Requirement & Matrix- Individual Subsystems Testing
- Status Light
- Saving
- Wake/Sleep Time Database
- Motors/Sun-Tracker
- Emergency Park
- Full System Testing
- Combined system initial tests
- Full day/weekend immersive tests
Design and Flowcharts
Risk Assessment
Design Review Materials
Plans for next phase
- Unfinished MSD-1 tasks
- Post construction
- Motor subsystem testing
- MSD Checklist
All testing and final creation of designed software is appropriate MSD-2 task
- Conclusion: We are ready to continue to MSD II
Home | Planning & Execution | Imagine RIT
Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design
Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation