P20071: Baseball Visual Swing Training
/public/

Customer Handoff & Final Project Documentation

Table of Contents

Team Vision for Final Demo and Handoff

Our team completed all final documentation for the project. The project is now set up so that a new team can take over and easily continue to improve the system.

Test Results Summary

We were able to get our program to output a relatively accurate exit velocity metric. This is a huge accomplishment for us considering the hectic circumstances of this semester. The end result of this project will not meet all of the design requirements, but we came very close despite all of the Covid-19 related issues.

Risk and Problem Tracking

Our risks and problems have not really changed since they were drastically altered during spring break.

Final Project Documentation


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation