Table of Contents

Team Vision for Build & Test Prep Phase

Test Plan Summary

Solenoid Validation Testing

Modified Solenoid Test Plan

Modified Solenoid Test Plan

Modified Solenoid Test Plan Flowchart

Modified Solenoid Test Plan Flowchart

ER1 & ER2 Testing

ER1 & ER2 Test Plan

ER1 & ER2 Test Plan

ER1 & ER2 Test Plan Flowchart

ER1 & ER2 Test Plan Flowchart

ER3 & ER4 Testing

ER3 & ER4 Test Plan

ER3 & ER4 Test Plan

ER3 & ER4 Test Plan Flowchart

ER3 & ER4 Test Plan Flowchart

= ER11, ER12 & ER13 Testing

ER11, ER12 & ER13 Test Plan

ER11, ER12 & ER13 Test Plan

ER11, ER12 & ER13 Test Plan Flowchart

ER11, ER12 & ER13 Test Plan Flowchart

ER15 & ER20 Testing

ER15 & ER20 Test Plan

ER15 & ER20 Test Plan

ER15 & ER20 Test Plan Flowchart

ER15 & ER20 Test Plan Flowchart

Use your test plan to summarize test results and assess effectiveness of test plans to unambiguously demonstrate satisfaction of the engineering requirements

Instructions

  1. Ensure test plans are in place
  2. Ensure that all applicable test standards have been cited (e.g., ASTM)
  3. Ensure all ordered materials have been received
  4. Ensure team has space and equipment necessary to begin building and testing

Risk and Problem Tracking

Risk Assessment

Risk Assessment

The link to the live document is here.

Design Review Materials

Include links to:

Plans for next phase

individual 3-week plan template


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Customer Handoff & Final Project Documentation