Build & Test Prep

Table of Contents

Team Vision for Build & Test Prep Phase

Summarize:

Test Plan Summary

Risk and Problem Tracking

Problem Tracking

Problem Tracking

Problem Tracking

Design Review Materials

Key Discussions:

Notes & Action Items from Review:

Plans for next phase

Task List for this Phase

Task List for this Phase

Note: "1" indicates critical path, "2" through "4" indicate importance where 4 is least urgent at this time. 20, 80, 100 or blank indicate percent completion.
Critical Path for MSD II

Critical Path for MSD II

Team Goals: (before next review)

Individual Goals: (before next review) See our 3 week plans {here}.