P20603: 3D Braiding Machine
/public/

Preliminary Detailed Design

Table of Contents

Team Vision for Preliminary Detailed Design Phase

Summary:

Accomplishments:

Mechanical System CAD

Horn Gear Bed

Horn Gear Bed

Bobbin path switcher

Bobbin path switcher

Close-up of plate bottom side with bobbin switcher installed

Close-up of plate bottom side with bobbin switcher installed

Bobbin path switcher in assembly

Bobbin path switcher in assembly

Plate which holds bobbin switcher

Plate which holds bobbin switcher

Horn Gear Dimensions

Horn Gear Dimensions

Feasibility: Prototyping, Analysis, Simulation

Simulation

Communication Methods

Communication Methods

Simulated Braid with a 3 X 3 bobbin grid

Simulated Braid with a 3 X 3 bobbin grid

Simulated Braid with a 3 X 3 bobbin grid

Simulated Braid with a 3 X 3 bobbin grid

Here is the link to the gif of the simulation

Prototypes

CAD for prototype bobbin track

CAD for prototype bobbin track

CAD for tension prototype

CAD for tension prototype

Tensioning mechanism on top of spool

Tensioning mechanism on top of spool

Drawings, Schematics, Flow Charts, Simulations

Wiring Layout

Wiring Layout

Bill of Material (BOM)

Bill of Materials

Bill of Materials

The BOM is used to organize the parts we expect to purchase and the CAD file name structure we are using.

Risk Assessment

Risk Management_1

Risk Management_1

Risk Management_2

Risk Management_2

Click the following link for the Risk Management active working document

Project Requirement Updates

Note: ER means Engineering Requirement, CR means Customer Requirement, and C means constraint

Design Review Materials

Action Items:

Plans for next phase

Team Plans

Individual Plans

Brandon

Allison

Shehaab

Angus

Asa

Ryan


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation